Skip to main content

Setup Base Calendars in #MSDynNAV & #MSDyn365bc.

 Hi Readers,

In last week #bcopendiscussion we discussed about Base Calendars.

With Microsoft Dynamics NAV and Business Central one of the feature that is not much talked about is Calendars.

With this feature you can define your working and non-working days which will also help in date calculations in Business Central.  

The main task in setting up a new base calendar is to specify and define the non-working days that you want to apply.

In this article, we will discuss about steps to setup Base Calendar.

Search for Base Calendar and Open Base as shown below.

Choose New Action and Provide a Name and description to Calendar.

Once Calendar is created, From Actions Ribbon Select Maintain Base Calendar Changes.


In Base Calendar changes window, use Recurring System field to mark a particular Date or day as a Recurring nonworking day.

You can choose - 

  • Annual Recurring.
    • Like Christmas or any other annual holiday based on your customer region.
  • Weekly Recurring.
    • Like Saturdays and Sundays.
  • Blank
    • Specific Day that applies for a particular year.


When you make an entry you can also provide a description and Nonworking field will automatically be selected.

Close and Open the calendar to see the impact.



Where in system you can define the calendar?
You can setup base calendar in - 

  • Company Information.
  • Customer.
  • Vendor.
  • Location.
  • Shipping Agent.
  • Service Management Setup.

Delivery and receipt dates on future sales order, purchase order, transfer order, and production order lines are calculated according to the calendar’s specified working days.

You can assign a base calendar to your company and its business partners, such as customers, vendors, or locations. 

Important - 
  • If you do not assign a base calendar to a company, all dates are calculated as working days.
  • If you enter a blank location on an order line, all dates are calculated as working days.
  • Any base calendar defined for the vendor or the location affects how the dates are calculated and rounded to working days.
How Base calendar Impact Lead Time Calculation - Read in MDSN.

You can also watch #bcopendiscussion session recording Youtube.

Stay Connected for More articles.

Regards,
Saurav Dhyani

Comments

Post a Comment

Popular posts from this blog

VIEW SERVER STATE permission on SQL Server?

Hi all, Sometime While trying to Login into a database we face an error message as shown below. --------------------------- Microsoft Dynamics NAV Classic --------------------------- You cannot start Microsoft Dynamics NAV Classic because you do not have the VIEW SERVER STATE permission on SQL Server. Contact your system administrator. --------------------------- OK    ---------------------------

RTC Report It is not possible to instantiate the Visual Studio bridge.

Hi all, As a Navision developers I have Multiple Versions of Navision running in single Machine. As discussed Earlier in the post how to run multiple Version of RTC in single machine. So my machine have following details for RTC Versions - NAV 2009 R2    - is installed. NAV 2009 SP1  - is copied at C:\Program Files (x86)\Microsoft Dynamics NAV\60\NAV 6.0 SP1 IN\ NAV 2009         - is copied at C:\Program Files (x86)\Microsoft Dynamics NAV\60\NAV 6.0 IN\ This approach has been working great for execution of Classic and RTC Clients. However, after installing Dynamics NAV 2009 R2, if i tried to view the Layout for an NAV 2009 SP1 Report i was getting the following error: ---------------------------  Microsoft Dynamics NAV Classic  ---------------------------  It is not possible to instantiate  the Visual Studio bridge.  ---------------------------  OK    --------------------------- After searchi...

NAV 2013 R2 - Cumulative update 12 Released.

Hi all, Please find below the details of  Cumulative Update 12 released for Microsoft Dynamics NAV 2013 R2. Title - Cumulative Update 12 for Microsoft Dynamics NAV 2013 R2 Build No. - 38053 Release Date - October, 2014 Local Version Included - AU, AT, BE, CH, DE, DK, ES, FI, FR, IS, IT, NA, NL, NO, NZ, SE, UK, RU Download Link Note: Implementing this cumulative update will require a database conversion unless you have already implemented update rollup 5.